RESOLVED that
1) the extension of the existing Learndirect contract only to August 2011 be noted and that Officers appraise Members at the earliest opportunity of the sustainability of the contract beyond this point; and
RECOMMENDED that
2) Option 4 as set out within the report (relocation of the Learndirect activity to another Council facility) be approved, subject to this being endorsed by Learndirect and that Officers be instructed to liaise with Learndirect as to validation and inspection arrangements; and
3) the costs of proceeding with Option 4 (£90,000) be approved, these costs to be met from revenue balances.